ĭrag to the left to shorten the duration of the part, or drag to the right to lengthen the duration. Hover over the right end of any part of the split task until the cursor changes to an expansion arrow. On the View tab, in the Task Views group, choose Gantt Chart.

You can also adjust the duration of each section of a split task: To change the duration of the entire split task (including all of its sections), type a new duration in the Duration field. In the Resource Leveling dialog box, select the Leveling can create splits in remaining work check box to allow splits as a result of leveling, or clear this check box to prevent splits during resource leveling. On the Resource tab, in the Level group, choose Leveling Options. Note: If your project has tasks that were already split, but you aren't sure why, your project may have been leveled while allowing splits to occur.